P&J performed site work and development services for this $240 million steel processing plant. The plant is expected to produce 350,000 tons of rebar each year from scrap metal, and it will also e...
View MoreP&J constructed a 350-acre solar site constructed as part of a local utility’s expansion of their use of alternative energy. In conjunction with approximately 12 other sites, this project is set...
View MoreP&J is responsible for construction of the WC-1 Clay Settling Dam Phase 1. Once complete, the 3.5-mile perimeter of the dam will reach an elevation of 177’ and encompass approximately 600 acres ...
View MoreThe Arden project is a mixed use planned development that will include residential units, recreational facilities, specialty retail space, and a future public school....
View MoreBlue Origin is constructing a new 750,000 SF orbital rocket manufacturing plant with the goal of manufacturing and launching its “New Glen” orbital rocket in 2020. This rocket factory is custom-bu...
View MoreP&J was subcontracted by Hensel Phelps, Construction Co. for the construction of Construction Management at Risk South Airport APM Complex Program Orlando International Airport....
View MoreP&J was contracted to complete all site work activities associated with construction of the Project Garden Distribution Center located on an 85-acre site in Lakeland, Florida....
View MoreThis project constructed an approximately 3 million square foot leach pad to stack and process the stockpiled ore located in a previously mined pit. Following construction of the leach pad and other s...
View MoreThis project is part of a $50M reclamation project for Rio Tinto’s Barney’s Canyon gold mine. This project includes soil remediation, extending liners, relaxing the slope of the heap leach pads, s...
View MoreThe L-8 Reservoir is a unique, 950-acre former rock mine with a watertight geology that allows for deep, below-ground storage of water which minimizes water loss through evaporation and eliminates lev...
View More