locations

Location

Wytheville, Virginia

contractor icon

P&J's Role

Prime Contractor

date icon

Completion Date

October 2018


Project Description

This project involved grading for a 5.3-acre substation pad expansion for the Jackson’s Ferry 765kV Substation located in Wytheville, Virginia. Total site disturbance of 24.47 acres was required for the installation of three  (3) storm retention ponds and relocation of the station’s access road. 

Project Highlights

89,900 CY

Cut to Fill

5.3

Acres of Fine Grade Pad

1,200

LF of Storm Drainage

P&J performed erosion control installation and maintenance, site grading, storm water installation, and final stabilization. Soil material had to be cut from underneath the existing 765kV conductor. P&J developed a comprehensive, site-specific safety plan to eliminate the possibility of incidents while working under the conductor.