P&J was contracted to complete all site work activities associated with construction of the Project Garden Distribution Center located on an 85-acre site in Lakeland, Florida....
Read MoreThis project constructed an approximately 3 million square foot leach pad to stack and process the stockpiled ore located in a previously mined pit. Following construction of the leach pad and other s...
Read MoreThis project was part of a $50M reclamation project for Rio Tinto’s Barney’s Canyon gold mine. It included soil remediation, extending liners, relaxing the slope of the heap leach pads, stormwater...
Read MoreThe L-8 Reservoir is a unique, 950-acre former rock mine with a watertight geology that allows for deep, below-ground storage of water which minimizes water loss through evaporation and eliminates lev...
Read MoreIn preparation for construction of a future cutoff wall, the Tennessee Valley Authority (TVA) sought to widen the crest of the earth embankment section of Boone Dam and improve its structural stabilit...
Read MoreThe C-51 Reservoir is a regional alternative water supply project for Southeast Florida designed to capture excess storm water currently wasted to tide and causing harm to the Lake Worth Lagoon. The ...
Read MoreThe Lower Bois d’Arc Creek Reservoir was constructed for the North Texas Municipal Water District to meet growing water demands in North Texas. The reservoir impounds more than 350,000 acre-feet of...
Read MoreThe Catawba River Water Supply Project is a two-year, off-channel reservoir expansion project that was constructed for a joint venture between Union County Public Works and Lancaster County Water and ...
Read More