This gold mine reclamation project includes soil remediation, extending liners, relaxing the slope of the heap leach pads, stormwater controls, and building demolition. P&J is responsible for approximately 2M CY of cut/fill reshaping, 1M CY topsoil load/haul/place, 30,000 TN aggregate hauling, and 400,000 CY of soil remediation. Project work also includes 3.0M CY of heap regrade and clean soils capping, 380,000 CY of sulfide ore excavation and encapsulation, 27,000’ of terrace channel and downdrain construction and 29,000 tons of aggregate placement.